| Height | 39 ft from the crown of the road, including mumtee and parapet; 32 ft without them; no second floor (Reg 23(a)) | A Phase 8 house is ground floor, first floor and mumtee. Extra space comes from the basement and from using the full first-floor allowance. |
| First floor | 100% of the ground floor on 5 Marla, 82% on 7 to 10 Marla, 80% on 1 Kanal, 78% on 2 to 4 Kanal (Reg 27(a)(3)) | On a 1 Kanal plot about 540 sq ft of ground-floor roof stays open. Plan it as a terrace off the family lounge or bedrooms, not as leftover roof. |
| Basement | Single storey; ceiling 9 to 14 ft; excavation no deeper than 12 ft including foundation, measured from the road crown; 5 ft back from a neighbour's dead wall (Regs 27(a)(1), 32(c) and 35) | Decide it before concept design. The basement fixes the plinth, the ramp, the sunken court and the structure. |
| Plinth and ramp | Plinth 1 ft 6 in to 3 ft 6 in above the road crown, up to 5 ft 6 in on 1 Kanal and above; 3 ft 6 in with a basement up to 10 Marla; ramp and clear spaces no more than 12 in above the crown (Regs 28 and 35) | On a new street, take every level from the road crown on your site plan, not from an empty neighbouring plot. |
| Floor heights | Ceilings at least 9 ft 6 in and living rooms at least 100 sq ft; no floor above 18 ft; one inter-floor from 9 Marla to 1 Kanal and two from 2 Kanal, each at least 8 ft clear (Reg 32) | A double-height lobby spans the ground and first floors instead of raising either. An inter-floor cannot hold a bath, kitchen, store, dressing room or wardrobe. |
| Mumtee | 175 sq ft up to 10 Marla; 300 sq ft from 1 to 4 Kanal; lift machine room 75 sq ft (Reg 33(a)) | Size the stair and any lift early. Living space is not allowed in the mumtee. |
| Swimming pool | Not on plots under 1 Kanal and never on the roof; 10 ft privacy wall (Reg 34) | Ivy Green's 5 and 10 Marla plots cannot take a pool; a 1 Kanal plot in Sector S, T, U or V can. |
| Services and security | Two CCTV cameras at both ends of the front boundary wall, a third on corner plots (Reg 66); generator up to 25 KVA, kept out of the rear and side clear spaces at ground level (Reg 58); solar only by PPIB-authorised vendors (Reg 67) | Show camera points, the generator position and the solar frame on the drawings, so the roof, parapet and electrical design are done once. |