Calculating Electrical Works requirements for any space involves a systematic approach, considering various factors like the type of Electrical Works, the specific application, and the overall design.
Electrical works cost in Pakistan
Electrical work is priced three ways here: per square foot of covered area, per point, and as a lump sum inside a construction contract. All three are published below for Lahore and Islamabad or Rawalpindi, with the manufacturer price list every figure is built from.
Rates reviewed 13 September 2026
Lahore, Standard specification, material and labour. Fittings and fans excluded.
Lighting and socket points, supply and fix. The fitting itself is not included.
About 3,100 sq ft of covered area in Lahore, Standard specification.
Discuss my project on WhatsApp
Avenir Developments prices electrical work as one package inside a construction or Design and Build contract for a whole house. We do not take standalone electrical or rewiring jobs. This page is published so plot owners and overseas clients can read the same numbers we work from, and check any quotation they receive against them.
What it costs, and which stage pays for it
Reviewed on 13 September 2026, complete electrical works for a new house in Lahore at a Standard specification cost PKR 240 to 320 per square foot of covered area. In Islamabad and Rawalpindi the same specification costs PKR 250 to 340. That covers cable, conduiting allowance, boxes, switches and sockets, distribution board and protection, earthing and labour. Light fittings, ceiling fans, solar equipment, UPS batteries and automation are separate.
On a 10 Marla house at about 3,100 square feet of covered area that is PKR 7.44 lakh to 9.92 lakh. On a 1 Kanal house at about 6,000 square feet, PKR 14.4 lakh to 19.2 lakh. On a 5 Marla house at about 1,900 square feet, PKR 4.56 lakh to 6.08 lakh.
Paid for in the grey structure
- Conduit routes in slabs, beams and walls
- Concealed boxes for switches, sockets and fan points
- Sleeves through slabs and walls
- Chasing of masonry ahead of plaster
- The DC conduit route from roof to inverter position
Paid for in the finishing
- Cable pulled through the conduit, every circuit
- Switches, sockets, plates and their termination
- Boards, breakers, residual current protection, main isolator
- Earth electrode, conductor and bonding
- Changeover for UPS or solar backed up circuits
- Testing, commissioning and the wiring test report
Ask any contractor in writing which stage carries conduiting and boxes. If both quotations include them you are paying twice. If neither does, the conduits will be missing when the wiring stage arrives, and the only fix is cutting chases into finished walls.
Planning ranges for budgeting, not quotations. A quotation needs drawings, a load schedule and a point schedule.
Estimate your own
Enter covered area, not plot area. Covered area is the total constructed floor area across all storeys, including the mumty and porch where they are roofed.
PKR 7.44 lakh to 9.92 lakh
744,000 to 992,000 rupees
Excludes connection and demand notice charges payable to LESCO or IESCO, solar panels, inverters and batteries, generator sets, lifts and automation hardware. A planning estimate, not a quotation.
Already holding a quotation? Send it to us.
We will read it against the schedules on this page and go through it with you: what it covers, what it quietly leaves out, and whether the rate is one the market can actually deliver. You are under no obligation to build with us.
- Plot size and city
- Covered area, if you know it
- The quotation itself, a photo is fine
- Whether it is grey structure, finishing or turnkey
Lahore and Islamabad or Rawalpindi. Architecture, construction and Design and Build.
Where the money is buried
Almost all of a house's electrical cost is covered over before anyone can inspect it. This is a cut section through a typical two storey house, with the eight elements that carry the cost keyed to the schedule below.
Tap a number on the drawing, or a row below, to link the two.
| Key | Element | Paid for in | Why it carries cost |
|---|---|---|---|
| 1 | Service cable and meter position | Grey structure | The distribution company brings the service cable to a meter box on the boundary wall. Its position fixes the route of the main incoming cable, and it is decided with the boundary wall, not afterwards. |
| 2 | Earth pit and earth conductor | Finishing | An electrode pit with salt and charcoal treatment, and a conductor run back to the board. A distribution company neutral is not an earth. This is the item most often missing from a cheap quotation. |
| 3 | Main distribution board | Finishing | Main isolator, residual current protection and one breaker per circuit. Four things change its cost: number of ways, isolator rating, shared RCCB or an RCBO per circuit, and breaking capacity. |
| 4 | Conduit cast in the slab | Grey structure | Every ceiling light and fan point is a conduit laid before the slab is poured. Once the concrete is placed the position is permanent. This sits in the grey structure rate, not the wiring rate. |
| 5 | Wall chases and concealed boxes | Grey structure | Switch and socket drops are chased into masonry before plaster. Adding a point afterwards means cutting the wall, repairing it and repainting, which is why late changes cost far more than they look. |
| 6 | First floor sub board | Finishing | A floor level board fed in 6 mm squared keeps circuit runs short and lets one floor be isolated without shutting down the house. Above 10 Marla it usually pays for itself in cable. |
| 7 | Air conditioner dedicated circuits | Finishing | Each split unit takes its own circuit in 4 mm squared with a dedicated breaker and an isolator beside the outdoor unit. Eight units instead of four is four more circuits, not a bigger cable. |
| 8 | Solar DC route and changeover | Grey structure | The conduit route from roof to inverter, the changeover position, and which circuits stay live on backup. All three are decided before the slab is cast, or the cable runs on the outside of the building later. |
Three of the eight sit in the grey structure and five in the finishing. That split is the reason two quotations for the same house can differ by a lakh and both look reasonable.
Where the electrical rupee goes
- Cable, all circuits36%
- Conduit, boxes and fixings12%
- Switches, sockets and plates8%
- Boards, protection and earthing7%
- Labour and supervision20%
- Contractor overhead and profit17%
Taken from the worked build up further down this page, for a 10 Marla house at Standard specification in Lahore. Two things are worth noticing. Copper is the largest single exposure in the package, which is why a manufacturer price revision moves the whole budget: between the Pakistan Cables lists effective 1 February and 3 June 2026, coil prices rose about 8.5 to 10 per cent. And contractor overhead and profit is 17 per cent of the total, a line most published electrical costings leave out entirely.
Rates by city and specification
Material and labour for a new build. Light fittings, ceiling fans, solar equipment and UPS batteries are excluded and added separately below.
| Specification | Lahore | Islamabad / Rawalpindi | Typical application |
|---|---|---|---|
| Starter | 175 to 240 | 180 to 250 | Rental or resale build, minimum viable point count |
| Standard | 240 to 320 | 250 to 340 | Owner occupied family house, most 5 and 10 Marla builds |
| Premium | 350 to 470 | 370 to 490 | 1 and 2 Kanal houses, designed lighting, higher point density |
| Luxury | 560 to 760 | 590 to 800 | Imported accessories, automation, full data and AV infrastructure |
| Addition | Starter | Standard | Premium | Luxury |
|---|---|---|---|---|
| Ceiling fans and light fittings | 55 to 95 | 90 to 160 | 180 to 330 | 360 to 650 |
| Solar and UPS readiness wiring | 25 to 40 | 35 to 60 | 55 to 90 | 80 to 140 |
Solar and UPS readiness covers the second distribution path for backed up circuits, the changeover arrangement, and the DC conduit route from roof to inverter. It does not cover panels, inverters, batteries or the net metering application.
Islamabad and Rawalpindi price about five per cent above Lahore. Cable and switchgear are made mainly in Karachi and Lahore and carry freight north, the twin cities wholesale market discounts less deeply on the same brands, and the distribution company is IESCO rather than LESCO. That five per cent is a working assumption from our own purchasing, not a published index.
What the materials cost today
Published manufacturer and retail prices, not Avenir rates. These are the inputs behind every figure above, and the numbers to check when a contractor tells you cable prices have moved.
| Size | Copper area | Typical circuit | Registered | Unregistered |
|---|---|---|---|---|
| 3/.029 | about 1.28 mm² | Lighting and fan circuits | 8,950 | 9,253 |
| 1.5 mm² solid | 1.5 mm² | Lighting circuits, earth conductor | 10,330 | 10,680 |
| 2.5 mm² solid | 2.5 mm² | Socket and small power circuits | 16,845 | 17,416 |
| 7/.029 | about 2.98 mm² | Socket circuits, 1 to 1.5 ton air conditioners | 19,735 | 20,404 |
| 4 mm² | 4 mm² | Air conditioner and geyser circuits | 26,010 | 26,892 |
| 6 mm² | 6 mm² | Sub main feeds to floor boards | 38,650 | 39,960 |
| 10 mm² | 10 mm² | Main incoming, solar DC runs | 66,810 | 69,075 |
| 16 mm² | 16 mm² | Main incoming on larger houses | 101,785 | 105,235 |
3/.029 is not 1.5 mm²
Imperial sizing gives the strand count and their diameter in inches. A 3/.029 cable is three strands of 0.029 inch, about 1.28 square millimetres of copper, so it carries less copper than a 1.5 mm² cable. A 7/.029 is seven strands, about 2.98 square millimetres, more copper than 2.5 mm².
The price list confirms it. The 3/.029 coil is 8,950 against 10,330 for 1.5 mm², about 13 per cent lower, tracking its 15 per cent lower copper content. The 7/.029 coil is 19,735 against 16,845 for 2.5 mm², about 17 per cent higher, tracking its 19 per cent extra copper. Copper is what you are buying. A coil offered well below these numbers for the same nominal size is short, thin, or copper clad aluminium.
Prices moved 8.5 to 10 per cent in four months
Comparing the Pakistan Cables list effective 1 February 2026 with the list effective 3 June 2026, the 3/.029 coil rose from 8,245 to 8,950 and the 7/.029 coil from 18,185 to 19,735, both about 8.5 per cent. The 6 mm² and 10 mm² sizes rose exactly 10 per cent, from 35,135 to 38,650 and from 60,735 to 66,810.
On a house where cable is roughly a third of the electrical package, a 10 per cent cable move is a 3 per cent move on the electrical budget. That is why every figure here carries a review date, and why a quotation held open for six months is not the favour it appears to be.
| Accessory | Indicative retail | Notes |
|---|---|---|
| Local unbranded switch or socket | PKR 130 to 400 | Avoid on kitchen, bathroom, geyser and air conditioner circuits |
| Clipsal by Schneider, 1 to 2 gang switch | PKR 550 to 1,500 | Vivace, Pieno and E Series ranges |
| Clipsal by Schneider, 13A switched socket | PKR 1,100 to 2,200 | Duplex and multi gang units price higher |
| Clipsal by Schneider, multi gang plate | PKR 2,100 to 6,600 | Five and six gang plates for lounges and stair cores |
| Panasonic switch or socket | PKR 850 to 3,000 | 13A BS socket and Cat 6 data socket sit in this band |
| Item | Indicative retail | What it does |
|---|---|---|
| MCB, 1 pole, 6A to 63A | PKR 250 to 650 certified local, 1,200 to 2,400 European brand | Overload and short circuit protection on one circuit |
| RCCB, 2 pole, 30 mA | PKR 1,500 to 4,200 | Earth leakage protection against electric shock |
| RCBO, per circuit | PKR 1,800 to 4,800 | Both in one module, so one faulty circuit does not trip the house |
| Board, 8 way plastic | PKR 1,650 to 2,800 | A small flat or a floor sub board |
| Board, 12 way | PKR 2,500 to 5,500 | Typical 5 to 10 Marla single phase house |
| Board, 18 way metal with door | PKR 3,400 to 7,500 | 10 Marla and above with several air conditioners |
A board described only as "DB with MCBs" is not a specification. What changes both cost and safety is the number of ways, the isolator rating, whether socket circuits sit behind a shared 30 mA RCCB or each carries its own RCBO, and the breaking capacity. Ask for those four in writing.
| Item | Size | Indicative price |
|---|---|---|
| PVC conduit pipe | 20 mm, three quarter inch | PKR 180 to 250 per length |
| PVC conduit pipe | 25 mm, one inch | PKR 250 to 350 per length |
| Conduit coupling | 20 or 25 mm | PKR 15 to 30 each |
| Conduit bend | 20 or 25 mm | PKR 20 to 40 each |
| Junction or pull box | Standard | PKR 60 to 150 each |
| Saddle or round block | 20 or 25 mm | PKR 8 to 15 each |
Conduit is the item most often mispriced in published costings, because it is quoted by the length and estimated by the metre. A three metre length at PKR 215 is about PKR 72 per metre, not the PKR 200 to 500 per metre that circulates on some cost pages.
| Category | Daily rate | Applies to |
|---|---|---|
| Skilled | PKR 2,000 | Electricians, masons, plumbers, welders |
| Semi skilled | PKR 1,560 | Assistants on skilled trades |
| Unskilled | PKR 1,538 | Helpers, labour |
| Monthly minimum | PKR 40,000 | Punjab, monthly employed workers |
These are the statutory floor rates the province notified, and they are what the labour element of every figure on this page is built from. The federal minimum wage rose to PKR 40,700 a month from 1 July 2026 under the 2026-27 budget. A working electrical gang on a house is one skilled electrician and one helper, PKR 3,538 a day between them.
You will not be on site the week the conduits go in
Which is the week the electrical decisions get buried in concrete. For clients in the UK, UAE, USA, Canada and Australia we run point marking, material approvals and stage reporting against drawings and photographs, so the decisions are made on evidence rather than on trust.
- Where you are, and where the plot is
- Plot size and whether drawings exist yet
- Who can access the site on your behalf
Roughly half of our clients build from overseas. See how that works.
Cost per point, and how many a house needs
A point is one accessory position with everything behind it: the conduit run, the box, the cable, the switch or socket and the termination. The downlight or the ceiling fan is not part of the point.
| Point type | Cost per point | Circuit |
|---|---|---|
| Light point, switched | PKR 2,900 to 4,000 | 3/.029 or 1.5 mm² |
| Fan point with regulator | PKR 3,600 to 5,000 | 3/.029 or 1.5 mm² |
| 5A socket point | PKR 2,900 to 4,000 | 1.5 mm² |
| 13A or 16A power socket | PKR 4,300 to 6,200 | 2.5 mm² or 7/.029 |
| Geyser or pump point | PKR 7,500 to 12,000 | 2.5 to 4 mm², dedicated breaker |
| Air conditioner point | PKR 11,000 to 17,000 | 4 mm², dedicated breaker and isolator |
| Data or television point | PKR 4,200 to 6,800 | Cat 6 or coaxial to a central position |
| Two way switching, per extra way | PKR 1,700 to 2,700 | Stairs, corridors, bedrooms |
| Plot size | Covered area | Typical points | Lahore | Islamabad / Rawalpindi |
|---|---|---|---|---|
| 5 Marla | 1,900 sq ft | 90 to 120 | PKR 4.56 to 6.08 lakh | PKR 4.75 to 6.46 lakh |
| 10 Marla | 3,100 sq ft | 140 to 190 | PKR 7.44 to 9.92 lakh | PKR 7.75 to 10.5 lakh |
| 1 Kanal | 6,000 sq ft | 250 to 340 | PKR 14.4 to 19.2 lakh | PKR 15.0 to 20.4 lakh |
| 2 Kanal | 10,000 sq ft | 420 to 560 | PKR 24.0 to 32.0 lakh | PKR 25.0 to 34.0 lakh |
The two methods reconcile, and that is the test to apply to any quotation. The worked build up further down this page puts a 165 point house at PKR 830,000 all in, which is PKR 5,030 per point and PKR 268 per square foot. Both land inside the bands above. If a contractor's per point rate and per square foot rate do not reconcile like this, one of the two is wrong, and it is worth asking which.
Included in the rate
- All cable for lighting, socket, power, air conditioner and geyser circuits
- Conduit allowance, boxes, junction boxes, bends and fixings
- Switches, sockets, plates and termination, to the specification
- Main and floor boards, breakers, isolator, residual current protection
- Earth electrode, conductor and bonding
- Doorbell, and data and television provision where shown
- Labour, supervision, testing and the wiring test report
Priced separately
- Light fittings, downlights, profile lighting and ceiling fans
- Solar panels, inverters, batteries and the net metering application
- UPS units and their batteries
- Generator sets and transfer switches
- Lift, gate motor and swimming pool plant power
- Air conditioner units and ducted systems
- Automation hardware, CCTV cameras and recorders, access control
- LESCO or IESCO demand notice, security deposit and meter charges
Covered areas use 225 square feet per Marla, the convention in DHA and most private schemes. Revenue records use 272.25. Check which basis a quotation uses before comparing rates.
What published cost figures leave out
These are the items that turn a quoted electrical budget into a larger final bill. None is exotic. All are avoidable if they are named before work starts.
Containment, counted twice or not at all
Conduit and boxes belong to the grey structure. Many finishing quotations price them again, and many grey structure quotations quietly leave them out.
Earthing
An electrode pit with salt and charcoal treatment, and the conductor run to the board, is a real line item. A distribution company neutral is not an earth.
Protection strategy
Number of ways, isolator rating, residual current strategy and breaking capacity change the cost of the board by a multiple.
Load sanction and the connection file
A wiring contractor's test report forms part of the new connection application. If the sanctioned load pushes the house to three phase, the meter, cable and board all change.
Solar and UPS changeover
Backed up circuits need a second distribution path and a changeover. The DC route from roof to inverter has to be decided before the slab is cast.
Fittings against points
On a Premium house the downlights, cove lighting and decorative fittings can cost more than the whole wiring package behind them.
Chasing and making good
Adding a point after plaster means cutting a chase, repairing it and repainting. That cost lands in the masonry and paint trades, not the electrician's quote.
Ceiling coordination
POP ceilings, cove details and duct routes fix the position of every downlight. Deciding after the ceiling is up means opening it again.
What moves the number
Point density, not floor area
Two houses of the same covered area can differ by 40 per cent. Kitchens, media walls, home offices and terraces carry far more points per square foot than bedrooms and corridors.
Air conditioning count and tonnage
Each split unit takes its own circuit in 4 mm squared with a dedicated breaker and isolator. Eight units rather than four adds four circuits, not a bigger cable.
Single phase against three phase
Above roughly 15 kW of sanctioned load a house usually moves to three phase, which changes the meter, the incoming cable, the board and phase balancing. Confirm the threshold for your address with your distribution company.
Ceiling type and lighting design
A full POP ceiling with cove lighting multiplies both point count and coordination effort against a plain slab soffit with surface fittings.
Solar readiness after the 2026 rule change
NEPRA replaced net metering with net billing under the Prosumer Regulations notified in February 2026, cutting the export rate for new applicants well below the retail import rate. Reported buyback figures have ranged from about PKR 8 to PKR 11 per unit and the position has been under review since. The design consequence is stable: self consumption is now worth far more than export, so wire for backed up circuits and daytime load shifting rather than for a large export system. Confirm the current rules before sizing anything.
External and ancillary loads
Boundary and facade lighting, gate motor, borewell pump, pressure pump, pool plant, lift and basement ventilation each add circuits outside the house point count.
What each specification contains
A specification name means nothing without named products. These are the electrical rows of Avenir's standard finishing specification, matching the tiers on our house construction cost page.
| Item | Starter | Standard | Premium | Luxury |
|---|---|---|---|---|
| Wiring cable | Certified local brand | GM or Fast Cables | Pakistan Cables or Newage | Pakistan Cables or Newage |
| Switches and sockets | Local | China | Imported | Imported smart |
| Protection and switchgear | Certified local breakers | Terasaki or equivalent, shared RCCB | Terasaki or equivalent, RCBO on wet and socket circuits | RCBO per circuit, surge protection |
| Conduit | Certified local PVC | GM or Plasco | Popular or Beta | Dadex |
| Ceiling fans | Local A quality | Local A quality | Local A plus brand | Inverter type |
| UPS wiring | Not included | Included | Included | Included |
| Data and television | Not included | Lounge and master bedroom | All bedrooms and study, central rack | Structured cabling throughout |
| CCTV provision | Not included | Not included | Cabling and positions | Cabling, positions and recorder point |
Where this says imported or local, the actual brand is fixed in the project BOQ before work starts, with the model range and plate finish. No substitution without written approval.
How the rate is built, line by line
Most published construction costs are a number with nothing behind it. This is the full build up for one house, so you can check every input, change any assumption, and see where the answer moves. It is the same calculation the estimator on this page runs.
| Line | How it is calculated | PKR |
|---|---|---|
| Cable | 24 coils: ten of 3/.029, seven of 7/.029, three of 1.5 mm², three of 4 mm², one of 6 mm². Priced on Schedule C the lot comes to 375,315, taken at 80 per cent because the Standard specification is GM or Fast Cables rather than the premium brand. | 300,252 |
| Conduit, boxes and fixings | 6 metres of conduit per point, so 330 lengths at 215. Plus 195 boxes at 100, and couplings, bends and saddles at 60 per point. Rates from Schedule F. | 100,350 |
| Switches, sockets and plates | 150 accessories at 450 each, the China grade band that sits between the local and Clipsal prices in Schedule D. | 67,500 |
| Boards, protection and earthing | 18 way main board, 12 way floor board, 28 breakers, two 30 mA RCCBs, main isolator and changeover, and earth pit materials. Rates from Schedule E. | 53,700 |
| Labour and supervision | One electrician at 2,000 a day and one helper at 1,538, from Schedule G, so 3,538 per gang day. 33 gang days on points at five points a day, eight gang days on boards, earthing and testing, plus 25,000 supervision. | 170,058 |
| Subtotal | Material and labour before the contractor's margin | 691,860 |
| Overhead and profit | 20 per cent. This is the line most published electrical costings leave out, and it is why their figures look achievable and then are not. | 138,372 |
| Total | PKR 268 per square foot over 3,100 sq ft, or 5,032 per point over 165 points | 830,232 |
What is sourced
- Cable prices: Pakistan Cables Limited suggested retail price list, effective 3 June 2026
- Conduit, boxes and fittings: Pakistani supplier trade listings, mid 2026
- Switches, sockets, boards, breakers and residual current devices: Pakistani specialist distributor listings, September 2026
- Labour: daily wage rates notified by the Punjab Finance Department, July 2026
What is assumed, and stated
- 165 points for a 3,100 square foot house at Standard specification
- 6 metres of conduit per point
- Five points completed per gang day across the full cycle
- Market brand cable at 80 per cent of the premium brand list
- Contractor overhead and profit at 20 per cent
Change any assumption and the answer moves in a way you can follow. Raise the point count to 190 and the figure goes up by about 12 per cent. Specify Pakistan Cables rather than a market brand and cable alone adds 75,000. That is the reason for publishing the build up rather than a single rate: a number you cannot interrogate is a number you cannot rely on.
The bands in Schedule A are this calculation run across the four specifications and across a realistic spread of point densities, then rounded to the nearest ten rupees. Starter drops to local cable and accessories and a lower point count. Premium moves to Pakistan Cables or Newage, imported accessories, an RCBO on every wet and socket circuit, and roughly a quarter more points. Luxury adds imported smart accessories, an RCBO per circuit and structured cabling throughout, which is why it runs to more than double Standard.
What a properly run electrical package needs
Electrical work is the part of a house easiest to get wrong quietly, because most of it is buried before anyone can inspect it. Seven things separate a package that holds up from one that does not, whoever builds for you.
- A load schedule before a rate. The appliances the household will actually run, air conditioners by tonnage, geysers, pumps, kitchen equipment and any UPS or solar arrangement, listed and totalled. The sanctioned load follows from that, not from a rule of thumb per Marla.
- A single line diagram and circuit schedule. Circuits, cable sizes, breaker ratings and residual current protection drawn and issued with the construction drawings, rather than decided by the electrician on site.
- Point marking walked before conduiting. Every switch, socket and light position marked on the wall at brickwork stage and agreed. This is the last moment a change is free.
- Conduit routes coordinated against the structural drawings. No chase cut into a beam or a column, and no conduit crossing a structural element the engineer has not allowed for.
- A reflected ceiling plan agreed before POP. Downlight, cove and diffuser positions fixed once, so the ceiling is not opened again after it is finished.
- Named brands and grades in the BOQ. Cable brand, accessory range, board make and breaker type written in, with substitution requiring written approval. Schedule J is what that looks like.
- Testing recorded before handover. Insulation resistance, earth continuity, polarity and residual current trip testing, the wiring contractor's test report for the connection file, and an as built circuit schedule inside the board door.
Avenir Developments prices the electrical package this way inside a construction or Design and Build contract for a whole house, in Lahore and Islamabad or Rawalpindi, alongside the structural and mechanical packages. We do not quote electrical works, rewiring or fault finding as a standalone service.
Review dates and limits
Rates reviewed 13 September 2026. Cable prices are next due for review by mid October 2026, or sooner if a manufacturer issues a new list.
Everything on this page is a planning range for budgeting. It is not a quotation, it is not electrical design, and it does not establish the sanctioned load, circuit design or protection strategy for any particular house. Those follow from drawings and a load schedule. Prices move: the cable inputs alone rose between 8.5 and 10 per cent in the four months between the February and June 2026 manufacturer lists, which is why every figure here carries the date it was reviewed.
Questions we get asked
How much does electrical work cost for a house in Pakistan?
For a new build in Lahore at a Standard specification, PKR 240 to 320 per square foot of covered area, reviewed 13 September 2026. That covers cable, conduiting allowance, boxes, accessories, distribution board and protection, earthing and labour. In Islamabad and Rawalpindi the same specification costs PKR 250 to 340 per square foot. Light fittings, ceiling fans, solar equipment and UPS batteries are separate.
Is electrical work part of grey structure or finishing?
Both. Conduit routes, concealed boxes, sleeves and chasing are cast or cut into the shell and belong to the grey structure. Cable, accessories, distribution boards, earthing and testing belong to the finishing. Ask any contractor which stage carries containment, because a quotation that prices it in both stages is charging you twice, and one that prices it in neither will need chases cut into finished walls.
How many electrical points does a 10 Marla house need?
Around 140 to 190 points for a 10 Marla house of roughly 3,100 square feet covered area at a Standard specification. A 5 Marla house at about 1,900 square feet typically runs 90 to 120, a 1 Kanal house at about 6,000 square feet runs 250 to 340, and a 2 Kanal house at about 10,000 square feet runs 420 to 560. Point density is driven by kitchens, media walls and home offices far more than by floor area.
What does one electrical point cost?
At Standard specification in Lahore, supply and fix, a light point costs PKR 2,900 to 4,000, a 5A socket point PKR 2,900 to 4,000, a 13A power socket point PKR 4,300 to 6,200, and a dedicated air conditioner point PKR 11,000 to 17,000. The light fitting or the ceiling fan itself is not included in a point rate.
What is the difference between 3/.029 and 1.5 mm² cable?
A 3/.029 cable has three strands of 0.029 inch, about 1.28 square millimetres of copper, so it carries less copper than a 1.5 mm² cable and is priced lower. On the Pakistan Cables list effective 3 June 2026, a 90 metre coil of 3/.029 is 8,950 against 10,330 for 1.5 mm². A 7/.029 has seven strands, about 2.98 square millimetres, more copper than 2.5 mm², and is listed at 19,735 against 16,845. Imperial and metric sizes are not interchangeable, and the price difference reflects the copper.
What is the current electric wire price in Pakistan?
On the Pakistan Cables suggested retail price list effective 3 June 2026, a 90 metre coil is 8,950 for 3/.029, 10,330 for 1.5 mm² solid, 16,845 for 2.5 mm² solid, 19,735 for 7/.029, 26,010 for 4 mm² and 38,650 for 6 mm², at the sales tax registered rate. Other manufacturers price below this list and project purchasing usually secures a discount. Prices rose about 8.5 to 10 per cent between the February and June 2026 lists.
Do I need a three phase connection?
It depends on the sanctioned load your appliances require, not on the plot size. Houses above roughly 15 kW of load are generally moved to three phase, which changes the meter, the incoming cable, the main board and how circuits are balanced. A load schedule produced at design stage settles this before the connection is applied for, rather than after the meter has been installed. Confirm the current threshold and process with LESCO or IESCO for your address.
Does solar change how a new house should be wired in 2026?
Yes. NEPRA replaced net metering with a net billing framework under the Prosumer Regulations notified in February 2026, and the export rate for new applicants was reduced well below the retail import rate. Reported figures for the new buyback have ranged from about PKR 8 to PKR 11 per unit, and the position has been subject to amendment since, so verify the current rules before committing. The design consequence has held steady regardless: self consumed units are worth far more than exported units, so a new house should be wired for backed up circuits and daytime load shifting rather than for a large export system.
What is a wiring test report and do I need one?
It is a certificate from a licensed wiring contractor confirming the installation has been tested, and it forms part of the document set submitted with a new electricity connection application to LESCO or IESCO alongside ownership proof, CNIC copies and a neighbouring bill. Requirements and the current document list should be confirmed directly with your distribution company or on the national new connection portal, since they are revised from time to time.
Does Avenir take on electrical work on its own?
No. Avenir Developments delivers electrical works as one package inside a construction or Design and Build contract for a complete house, in Lahore and Islamabad or Rawalpindi. We do not quote standalone wiring, rewiring, fault finding or electrical maintenance. These cost pages are published so that plot owners can budget properly and check the quotations they receive, whoever ends up building for them.
Price the whole house, not one trade
Three lines is enough to begin. We will come back with a realistic total budget, the electrical package sitting inside it where it belongs, and a plain answer if the budget and the brief do not meet.
- Plot size and city
- How many storeys, and whether you want a basement
- The specification you have in mind, or ask us to suggest one
Architecture, construction and Design and Build in Lahore and Islamabad or Rawalpindi. We do not take standalone electrical work.